Architecture & Design · Intermediate
Draft RFI responses from the spec and drawings
RFI 047 arrives at 4:50 on a Thursday: the hardware schedule calls for a closer on the stair door, the elevation shows a hold-open, and the contractor needs to order this week. The answer is somewhere in three specification sections and two drawings. A fast answer that's wrong costs more than a slow one that's right, and an answer that quietly changes the work costs most of all. This guide drafts cited responses quickly and flags the answers that aren't really RFI answers at all.
What AI is for here, and what it isn't
A request for information (RFI) asks the design team to clarify the contract documents. A good response does three things: it answers the question, cites where in the documents the answer comes from, and stays an answer. If the answer changes the work, it isn't really an RFI response any more. It's a change, and the contract has its own procedures for changes.
AI helps with the search and the drafting. Give it the RFI and the sections and notes you've pulled, and it will find the relevant paragraphs, draft a response that cites them, and point out where the specifications and drawings seem to disagree. That turns a 45-minute hunt into a 10-minute review.
It can't make design decisions, and it doesn't know your project's history: what was value-engineered out, what the owner asked for in a meeting six months ago, or why that door is different from the others. It will also cite paragraphs confidently, including ones that aren't in the text you gave it. And it only reads the text you extract. Drawings carry much of their meaning graphically: door swings and hardware symbols, fire-rating lines, dimensions, and how a detail relates to the plan it's cut from. None of that survives as copied notes, so the drawings themselves must be checked by a person. The architect decides the design answer and any implication for cost or schedule. The AI drafts, cites and flags.
Pull the relevant documents
Read the RFI and pull what it touches. Usually that means:
- The specification sections named in the RFI, and those they reference. For a door hardware question, for example: Section 08 71 00 (Door Hardware), the door and frame section, and often the fire-rated assembly requirements.
- Drawing notes and schedules: the door schedule, hardware sets, the relevant plan, elevation and detail notes. Copy the text and note the sheet numbers.
- The drawings themselves: open the actual sheets the question touches, not just their notes. Look at the plan, elevation, details, symbols, ratings and dimensions, and how they relate to each other. The AI works from the extracted text; you check what it can't see.
- Previous RFIs, supplemental instructions and change documents on the same topic, so the answer is consistent with what's already been said.
Draft a cited response
Give the AI the RFI and the excerpts you pulled, and nothing else. The prompt asks for a short answer, a citation for every statement, and a separate check on whether the answer changes the work. That check is the most important part of the draft.
Draft a response to this RFI using ONLY the documents below. I will
review and decide the answer.
RFI: [number, question, contractor's proposed solution if any]
SPECIFICATION TEXT (section numbers and paragraph numbers included):
[paste]
DRAWING NOTES (with sheet numbers): [paste]
PREVIOUS RFIs / ASIs ON THIS TOPIC: [paste or "none"]
PRODUCE:
1. RELEVANT PROVISIONS: each one quoted, with section/paragraph or
sheet number.
2. DRAFT RESPONSE: two to five sentences answering the question and
citing the provisions. Plain, specific, no hedging.
3. CONFLICTS: any place where the specifications, drawings or previous
responses disagree with each other. Quote both sides.
4. CHANGE CHECK: does the draft response require anything beyond what
the documents already require (added work, different product,
different quantity)? If yes, say exactly what, and label it
POSSIBLE CHANGE — NOT AN RFI ANSWER.
5. MISSING: documents you'd need to answer with confidence.
RULES: Cite only paragraphs in the supplied text. If the answer isn't
in the documents, say so; don't fill it in.
The change check is the core of this step. Most RFI trouble starts with an answer that slipped in a change.
Decide the answer
Review the draft against the documents, then make the call yourself:
- If the documents answer it: confirm each citation against the actual specification text and the actual drawing sheets (not the extracted notes), tighten the wording, and send it.
- If the documents conflict: resolve it under the contract actually signed for this project. Don't assume drawings beat specifications or the reverse: the standard AIA general conditions (A201) treat the contract documents as complementary and set no automatic hierarchy between them. Check the executed agreement, its supplementary conditions and amendments (which may add an order of precedence), and the architect's authority under that contract to interpret the documents. State the decision and its basis. If it changes the work, it isn't an RFI answer.
- If it's a change: answer the RFI by saying so, and start the right procedure. On contracts using the AIA documents, that's typically an architect's supplemental instruction (G710) for a minor change with no cost or time impact, or a proposal request leading to a change order or construction change directive where cost or time may change. Tell the owner when cost or schedule may be affected.
Log it
Record every RFI: number, date received, question, response, date answered, who answered, and whether it led to a change document. A log makes patterns visible, such as the same detail generating three RFIs, and shows response times if anyone later claims delay.
Worked example: RFI 047
Fictional example. RFI 047: "Door 214 (stair) is scheduled with hardware set 6 (closer, no hold-open). Elevation A-501 shows a magnetic hold-open. Please confirm which is required. Hold-open hardware has a 6-week lead time."
The project architect pastes Section 08 71 00, the hardware sets, the door schedule, sheet A-501's notes and the fire-rating notes on the life safety plan. She also opens the sheets themselves: the life safety plan shows door 214 in a rated stair enclosure, and the elevation shows the hold-open symbol, neither of which is in the copied notes.
The draft response cites hardware set 6 and the door schedule, which both show a closer and no hold-open. It flags a conflict with the A-501 elevation note, and adds:
CHANGE CHECK — POSSIBLE CHANGE: If the hold-open shown on A-501 is required, it would need an electromagnetic holder tied to the fire alarm system so the door releases and closes on alarm. That adds hardware and fire alarm work not included in hardware set 6.
The architect checks the history. The hold-open was in an early design and removed during value engineering, but the elevation note was never updated. The response:
Provide hardware set 6 as scheduled (Section 08 71 00 and door schedule, sheet A-601). The magnetic hold-open note on elevation 3/A-501 is superseded and will be removed in the next revision. No change to the work.
A one-line architect's supplemental instruction records the drawing correction. The contractor orders the closer that week. If the AI's draft had simply chosen the elevation, the project would have bought six weeks of lead time and an unbudgeted fire alarm change.
The response and log format
RFI [number] — [project] — Received [date] — Answered [date]
Question: [verbatim]
RESPONSE
[answer, two to five sentences]
REFERENCES
- Section [nn nn nn], paragraph [n.n.n]
- Sheet [A-nnn], [detail/note]
CHANGE TO THE WORK: none / see [ASI / proposal request number]
Answered by: [name, firm]
AI assistance: draft prepared with [tool]; answer and citations
confirmed by [name]
RFI LOG
No. | Received | Topic | Spec/Sheet | Answered | By | Change doc | Days to answer
What stays with you: the design answer, and any cost or schedule implication.